- Home
- Project Portfolio
- GM Orion
UPI is working across the entire Orion facility and was selected as the Engineer of Record (EOR) for chilled water and hot water.
PAINT SHOP (GK)
PT/ED
Process and building mains
Kais-AIR® air house piping
Paint circ / mix rooms & automation
Sealer piping & automation
Process decks & booths
Storm piping
Plumbing
Sludge
RTO piping
Gas & utilities to all ovens
Conveyor pneumatic piping & lubrication
POWERHOUSE
Design – Build
10 chillers, 8 boilers, 10 cooling towers, pumps & all ancillary equipment
Mechanical piping
Electrical and controls
CENTRAL UTILITY COMPLEX
Design – Build
5 chillers, 4 boilers, cooling towers, pumps and all ancillary equipment
Mechanical piping
Electrical and controls (Commerce Controls)
BODY SHOP
Weld water mains
Chilled water & hot water mains
Condensate
Kais-AIR® air house piping
Natural gas piping & equipment
WELD WATER CUC’s
Two (2) WW module plants feeding both
the new & existing body shops
Design – Build & shop built off site
Includes structural, architectural, controls, electrical, fire protection & mechanical
BATTERY ASSEMBLY BUILDING
Mechanical piping
Kais-AIR® air house piping
Condensate
Natural gas piping & equipment
EXISTING BODY & GA
Weld water mains
Mechanical piping
Natural gas piping & equipment